[ad_1]
As many as 384 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.66 lakh crore, as per a report.
According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and above, out of 1,514 projects, 384 reported cost overruns and as many as 713 projects were delayed.
“Total original cost of implementation of the 1,514 projects was Rs 21,21,471.79 crore and their anticipated completion cost is likely to be Rs 25,87,946.13 crore, which reflects overall cost overruns of Rs 4,66,474.34 crore (21.99 per cent of original cost),” the ministry’s latest report for June 2022 said.
According to the report, the expenditure incurred on these projects till June 2022 is Rs 13,30,885.21 crore, which is 51.43 per cent of the anticipated cost of the projects.
However, the number of delayed projects decreases to 552, if the delay is calculated on the basis of the latest schedule of completion.
Further, it showed that for 523 projects neither the year of commissioning nor the tentative gestation period has been reported.
Out of the 713 delayed projects, 123 have overall delays in the range of 1-12 months, 122 have been delayed for 13-24 months, 339 projects for 25-60 months and 129 projects have been delayed for 61 months and above.
The average time overrun in these 713 delayed projects is 42.13 months.
Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.
Delay in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems are among the other reasons.
The report also cited state-wise lockdowns due to COVID-19 as a reason for the delay in implementation of these projects.
It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it stated.
(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)
Dear Reader,
Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.
We, however, have a request.
As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.
Support quality journalism and subscribe to Business Standard.
Digital Editor
[ad_2]
Source link